Both replicas, the Kingdome took 3 weeks and Shea took 1. I used seating chart images and converted them to schematics and then built on top of them to get the size perfect.
Kingdome was started on May 21st, completed June 16th.
Shea Stadium was started June 17th, and completed on June 23rd.
Copyright 2010-2012 CoolBeanz Inc.
Kingdome was started on May 21st, completed June 16th.
Shea Stadium was started June 17th, and completed on June 23rd.
Copyright 2010-2012 CoolBeanz Inc.